Dogger Bank D: Huge new substation earmarked for land next to ancient woodland to take electricity from offshore wind farm

A huge new substation planned for farmland next to an ancient woodland in East Yorkshire will take electricity from the fourth phase of the world’s largest offshore wind farm.

Dogger Bank D will plug into the National Grid via a new 400kV substation at Birkhill Wood, built as part of the “Great Grid Upgrade”.

The substation, with equipment up to 13m high, will be built on seven acres, 700m to the northwest of the Creyke Beck substation, near Cottingham, which will also be extended.

Hide Ad
Hide Ad

Owners SSE Renewables and Equinor said the confirmation of the grid connection ruled out the use of electricity from Dogger Bank D towards hydrogen production at a dedicated onshore facility, as publicly consulted on last Autumn.

Birkhill Wood substationBirkhill Wood substation
Birkhill Wood substation

They are exploring the future possibility of building a multi-purpose interconnector which would link in with another European country as part of the Dogger Bank D project.

A statement said: “This option would increase energy security for the UK and reduce the need to curtail offshore wind output in times of oversupply on the GB network.”

The project team are undertaking a site selection process to identify potential cable corridors and where other onshore infrastructure associated with the grid connection at Birkhill Wood may be sited. The connection proposals will be consulted on with the public later this year.

Hide Ad
Hide Ad

Project Manager Rob Cussons said: "Dogger Bank D promises to build on the legacy we’re creating through the earlier phases of the Dogger Bank Wind Farm, during which we are working hard to deliver safe and respectful construction both offshore and onshore, as well as generating socio-economic value for current and future generations.” A planning application for the substation is expected to be submitted this summer.