Costain to build new bridge across River Thames
The firm said it had received the go-ahead from Surrey County Council to construct the bridge between Walton and Shepperton as part of a 32.3m scheme.
The Walton bridge is due to be completed in 2013 and will replace two temporary bridges in the area.
Advertisement
Hide AdAdvertisement
Hide AdThe government has agreed to contribute just under 23.9m to the project with the council providing a further 8.5m.
Shares in Costain closed Friday at 225 pence, valuing the business at 143m.